Changes between Version 12 and Version 13 of GENIRacksHome/InstageniRacks/AcceptanceTestStatus/IG-ADM-4


Ignore:
Timestamp:
02/15/13 13:06:52 (11 years ago)
Author:
tupty@bbn.com
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • GENIRacksHome/InstageniRacks/AcceptanceTestStatus/IG-ADM-4

    v12 v13  
    5353The site administrator should review the Emergency Stop procedure provided by the GMOC as well as the InstaGENI sliver shut down procedure.  The site administrator should identify parts of the procedure where they need to take action on the aggregate, and where they might need to interface with another party, such as the GMOC or an experimenter.  This parts identified by the site administrator should be verified with the GMOC and with the InstaGENI team.
    5454
    55 = Step 2 (prep): GPO, GMOC, and InstaGENI team coordinate a time to run an ES test =
     55= Step 2 (prep): GPO, GMOC, and InstaGENI team coordinate a time to run an Emergency Stop test =
    5656
    5757The GPO will coordinate with parties at the GMOC and on the InstaGENI team to identify when an Emergency Stop test can be run.  This test will focus primarily on the interactions with the site administator(s) and performing the procedures documented by the rack team.  The following roles will need to be defined for this test:
     
    9191
    9292'''Verify:'''
    93  * The shut down procedure includes the complete set of steps to
    94  * The shut down procedure results in a sliver being deactivated on a rack
     93 * The shut down procedure includes the complete set of steps shut down a sliver in the rack
     94 * Following the shut down procedure results in a sliver being deactivated on a rack
    9595 * Experimental traffic from the sliver is no longer being sent
    9696