== ExoGENI Acceptance Tests Open Topics == == Open Topics: 2013-02-27 == === Experimenter Tests === __Overall for Experimenter tests:__ ---> Expected Date: ??? [[BR]] Waiting on installation for AM API fix in all racks, to re-run experimenter acceptance tests. __EG-EXP-3: ExoGENI Single Site 100 VM Test__ ==> Expected Date: After GEC16 [[BR]] Need to rerun when hybrid mode is available. === Administrative Tests === __EG-ADM-2: Rack Administrator Access Test__ ==> Expected Date:__ ??? [[BR]] There are concerns about the current ExoGENI Control Network, and following are requests to address our concerns: 1. We think site admins will find it surprising and possibly alarming that part of their network (vlan 1006) is being bridged to control networks at other sites. It should be documented clearly for site admins that this is the case. 2. We think the IMMs at each site should have per-site nontrivial passwords (the ones at BBN are still trivial for example), so that accidental tampering with other sites' nodes is less likely. 3. We think site admins shouldn't be able to login to other sites' head nodes. This is a bit of extra protection against accidents which we think should be easy to implement. __EG-ADM-4: Emergency Stop Test__ ==> Expected Date: ??? [[BR]] An Emergency Stop Procedure detailed test outline is being defined. The preparation steps are currently being executed and Coordination is taking place. There are no blocking issues at this time. __EG-ADM-7: Documentation Review Test__ ==> Expected Date: ??? [[BR]] Email with prioritized documentation list was sent to the exogeni-design list. We would like to see some progress on the high priority items before GEC. === Monitoring Tests === __EG-MON-3: GENI Active Experiment Inspection Test__ ==> Expected Date: March 1-8 prep, March 11-? execution. [[BR]] GPO staff currently learning the Pequod interface, ramp up time is only issue. __EG-MON-5: GMOC Data Collection Test__ ==> Expected Date: [[BR]] Test is hindered by a GMOC bug, but workaround is available and being used. More work to be done by the ExoGENI, as discussed in Monitoring Call discussions. May need Victor and/or Jonathan's time to finish.