Cisco GENI Rack Acceptance Test Status
Test | State | Date Completed | Tickets/Notes |
CG-EXP-1: GENI AM API compliance | Color(yellow,Complete)? | 2014-12-09 | Advertisement problems: 1)unknown component id; 2)NCSU-only unkown hardware type; 3)Bad Advertisement schema (NCSU-only); no VLAN NCSU2-only; |
CG-EXP-2: Resource Allocation | Color(yellow,Complete)? | 2014-12-08 | Memory Allocation error reported at login on NCSU2; Embedding workflow error for bare metal, can only be tested at WVN |
CG-EXP-3: ExoGENI Stitching Support | Color(orange,Blocked)? | Embedding workflow error for pt-pt from NCSU to WVN; NCSU2 to WVN2 is future | |
CG-EXP-4: GENI Stitching Support | Color(yellow,Complete)? | 2015-01-09 | Blocked on dependencies: 1)Stitching path set-up to GENI core dependency; 2) remoteLinkId definition; 3) Stitching is configured only on NCSU2 |
CG-EXP-5: OpenFlow Support | Color(#63B8FF,In Progress)? | Completed OF Shared VLAN interoperability tests. To be tested OF over stitched connections. Waiting on stiching set up | |
CG-EXP-6: Limits Tests | Color(yellow,Complete)? | 50 2VMs-slivers ok at NCSU, some fail at NCSU2;25 VM grid fails; 10 slices with 10 VMs ok | |
CG-ADM-1: Administrative Functions | Color(green,Pass)? | No hostname aliases for rack switches; | |
CG-MON-1: Monitoring Functions | N/A | No monitoring tests are taking place in this stage of evaluation |
State Legend | Description |
Color(green,Pass)? | Test completed and met all criteria |
Color(#98FB98,Pass: most criteria)? | Test completed and met most criteria. Exceptions documented |
Color(red,Fail)? | Test completed and failed to meet criteria. |
Color(yellow,Complete)? | Test completed but will require re-execution due to expected changes |
Color(orange,Blocked)? | Blocked by ticketed issue(s). |
Color(#63B8FF,In Progress)? | Currently under test. |