GEMINI v1.1 Integration Plan and Status
Legend |
Color(green,Complete)? |
Color(#B0E0E6, In Progress)? |
Color(yellow, Blocked)? |
Color(#FF6600, "Won't Fix")? |
Not Started |
Task List and Status
ID | Task | Owner | Due | Status | Notes/Deliverables |
1 | Send list of Blipp graphs to KY | Ahmed | 10/8 | Color(green,Complete)? | |
2 | Set up MS dev instance | Ahmed | 10/8 | Color(green,Complete)? | |
3 | Send data access code to Jeremy | Ahmed | 10/8 | Color(green,Complete)? | |
4 | Package, instrumentize, and test Blipp/UNIS/MS | Ezra and Matt | 10/12 | Color(#B0E0E6, In Progress)? | Deliverables are a new tarball and install script |
5 | Integrate Blipp graphs into drupal | Jeremy and Charles | 10/11, 10/15 | Color(#B0E0E6, In Progress)? | Deliverables are new drupal configuration installed on the GN |
6 | Run Acceptance tests on all supported configurations | Jeanne | 10/22 | Color(#B0E0E6, In Progress)? | |
7 | Compose tutorial wiki | Jeremy and Ahmed | 10/12 | Color(#B0E0E6, In Progress)? | 1st draft by 10/12, iterate the week before GEC |
8 | Define topology, produce initial rspec | Jim and Charles | 10/10 | Color(#B0E0E6, In Progress)? | |
9 | Set up and verify half of slices for tutorial | Ezra | 10/12 | Not started | |
10 | Set up rest of slices for tutorial | Ezra | 10/15 | Not started | |
11 | Create information sheet | Jeanne | 10/22 | Not started | |
12 | Create accounts for path controller | Charles | 10/19 | Not started | |
13 | Verify resource allocation for tutorial | Jim | 10/12 | Color(#B0E0E6, In Progress)? |