    21== Project Status Report – October 2012 ==
    3 '''
     2
    43Period: 11/1/2011 – 10/31/2014
    5 '''1. Major Accomplishments
    6 '''
    7 The main accomplishments this quarter were 1) following up with the students who attended the first GENI research and educational experiment summer camp (GREE-SC2012), 2) planning the second GENI research and educational experiment workshop (GREE2013), to be held in March 2013 at the University of Utah, and 2) planning the second GENI research and educational experiment summer camp (GREE-SC2013), to be held in June 2013 at the University of Connecticut.
    84
    9 '''1.1. Milestones Achieved
    10 '''
     5==1. Major Accomplishments ==
     6
     7The main accomplishments this quarter were 1) following up with the students who attended the first GENI research and educational experiment summer camp (GREE-SC2012), 2) planning the second GENI research and educational experiment workshop (GREE2013), to be held in March 2013 at the University of Utah, and 2) planning the second GENI research and educational experiment summer camp (GREE-SC2013), to be held in June 2013 at the University of Connecticut. [[br]]
     8
     9
     10== 1.1. Milestones Achieved ==
     11
    1112Three major milestones were achieved during this period.
    12 1) All the graduate students who attended GREE-SC2012 are actively using GENI resources for their research projects and planning to submit their work to GREE2013, 2) we have been actively planning and advertising GREE2013, and 3) we have been actively planning and advertising GREE-SC2013.
    13 '''1.2 Deliverables Made
    14 '''
     131) All the graduate students who attended GREE-SC2012 are actively using GENI resources for their research projects and planning to submit their work to GREE2013, 2) we have been actively planning and advertising GREE2013, and 3) we have been actively planning and advertising GREE-SC2013. [[br]]
     14
     15== 1.2 Deliverables Made ==
     16
    1517The past four months of work on ARPA-GENI have resulted in progress towards three deliverables: 1) the following-up of the students who attended GREE-SC2012, 2) the GREE2013 flyer, and 3) the 2013 GENI summer camp flyer.
    1618