Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • ABAC-QSR-4Q2009

    v1 v1  
     1[[PageOutline]]
     2
     3= ABAC Project Status Report =
     4
     5Period: Oct 2009 - Dec 2009
     6
     7== I. Major accomplishments ==
     8Initial familiarization with the goals and objectives of the project.
     9
     10=== A. Milestones achieved ===
     11None
     12
     13=== B. Deliverables made ===
     14None
     15
     16== II. Description of work performed during last quarter ==
     17This effort commenced at SPARTA on December 5th, 2010, as the contract was not completely executed until Nov 13th, 2010, and the subsequent Thanksgiving holiday meant that technical and contract staff were not available to begin the effort until early December.
     18
     19A very modest number of hours (less than 2 staff days) were spent in beginning our understanding of the current state of the ProtoGENI control framework, with an aim toward indentifying a candidate software element within that control framework that would be a suitable target for integration with the current ABAC implementation.
     20
     21=== A. Activities and findings ===
     22No initial activities beyond beginning to investigate ProtoGENI.
     23
     24=== B. Project participants ===
     25The following SPARTA staff are participating in the ABAC project: Stephen Schwab, Jay Jacobs.
     26
     27=== C. Publications (individual and organizational) ===
     28None.
     29
     30=== D. Outreach activities ===
     31None.
     32
     33=== E. Collaborations ===
     34As the project has just started, we have not had time to collaborate with other groups, beyond seeking pointers to the current ProtoGENI documentation.
     35
     36=== F. Other Contributions ===
     37None.
     38