    1313|| Acquire and implement GENI wavelengths (EBC <-> Level3, DDC <-> EBC) ||      Complete ||      ||      || ||
    1414|| Acquire and implement UEN GENI DDC switch || Complete ||      ||  ||  ||
    15 || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || Complete ||  || ||  ||
    16 || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) || Complete || || || ||     
     15|| Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. || Complete ||  || ||  ||
     16|| Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. || Complete || || || ||   
    1717|| Work with Univ of Utah Flux group to install large InstaGENI rack at DDC || Complete ||  ||  || ||
    1818||  ||  || || || ||
    1919
    2020=== B. Deliverables made ===
    21  * GEC : attended by Steve Corbato and Joe Breen with poster
    22  * GEC : attended by Steve Corbato and Joe Breen
    23  * GEC : attended by Steve Corbato and Joe Breen
    24  * FOAM and Flowvisor upgrades complete
     21 * GEC 15: attended by Joe Breen
     22 * GEC 16: attended by Steve Corbato and Joe Breen
     23 * GEC 17: attended by Joe Breen
     24 * Ongoing maintenance - FOAM and Flowvisor upgrades complete, implementation of additional OpenFlow VLANs
    2525 * Deployed UEN Aggregate Switch at Downtown Data Center
    26  * Collaborated with Univ of Utah to bring up large InstaGENI Rack
     26 * Collaborated with Univ of Utah Flux Group to bring up large InstaGENI Rack
    2727 * Deployed two 10G wavelengths dedicated for GENI between DDC and EBC and between EBC and Level3
    2828
     
    3030=== A. Activities and findings ===
    3131 * Put together design and reviewed with GPO and Utah Experimenter team
    32  * Installed HP 5406v2 in the Utah Education Network EBC data center
     32 * Installed HP 5406v2 in the Downtown Data Center
    3333 * Setup FOAM and Flowvisor on virtual machine for controlling the UEN aggregate switch
    34  * Tested control of FOAM
     34 * Installed GENI wavelengths
    3535
    3636=== B. Project participants ===
    3737 * Steve Corbato - PI - University of Utah/UEN
    38  * Joe Breen -
     38 * Joe Breen - CHPC
    3939 * Kevin Quire - UEN Senior Network Engineer
    4040 * Jim Stewart - UEN Technical Director