    1             = Project 1861 Univ of Utah/UEN GENI Regional Project Status Report =
     1            = Project 1861 Univ of Utah/UEN GENI Regional Project Annual Status Report =
    22
    33== Period: 2012 Spiral 4 ==
     4
     5== Overview ==
     6In the 2012 Spiral 4 implementation, the Univ of Utah/UEN GENI Project 1861 successfully implemented and integrated the switch infrastructure that tied together the first InstaGENI installation at the Emulab/Flux/ProtoGENI environment to the GENI backbone in Los Angeles.  By leveraging network resources from the Univ of Utah, UEN, ProtoGENI, Internet2, and the GENI backbone, this project was able to put together the infrastructure necessary to support the first implementation.  Personnel resources from the Univ of Utah, ProtoGENI, UEN, Internet2 and the BBN GPO were all instrumental in making this implementation a success.  The Univ of Utah/UEN GENI Project 1861 did not receive funding until February/March 2012.  The project then proceeded in a fashion that accommodated researcher experimental timeline needs and some of the development of the Univ of Utah/UEN data center and metro optical fiber and DWDM implementation.  The project progresses forward on its upcoming milestones for the 2013 year.
    47
    58== I. Major accomplishments ==
    69=== A. Milestones achieved ===
    710|| '''Milestone''' ||   '''Status''' ||         '''Begin Date''' ||     '''End Date''' ||       '''Notes''' ||
    8 || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack ||    Complete ||     April 2012 ||   June 15, 2012 || First rack is Rob's InstaGENI rack ||
     11|| Acquire and test HP aggregate switch for ProtoGENI and first GENI rack ||    Complete ||     April 2012 ||   June 15, 2012 || First rack is Rob Ricci's initial InstaGENI rack ||
    912|| Deploy aggregate switch and bring new connections to Univ of Utah and UEN || Complete ||     June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation - involves interruption of current ProtoGENI infrastructure ||
    1013|| Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || Complete || July 1, 2012 || Aug 22, 2012 || Did not use UEN aggregate switch - Used only ProtoGENI direct connection into the GENI backbone.  Could not interrupt the experiments for the data plane cutover ||
    11 || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) || || Sept 23, 2012 || Sept 30, 2012 || || 
    12 || Make Switch resources available to NSF experimenters || || Sept 23, 2012 || Sept 23, 2012 || ||
    13 
     14|| Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) || Complete || Sept 23, 2012 || Sept 30, 2012 || ||
     15|| Make Switch resources available to NSF experimenters || Complete || Sept 23, 2012 || Sept 23, 2012 || ||
     16|| Aggregate page documentation setup || Complete || || Sep 30, 2012|| ||
    1417
    1518=== B. Deliverables made ===