= Project 1861 Univ of Utah/UEN GENI Regional Project Status Report = == Period: Through 9/30/2012 == == I. Major accomplishments ΒΆ == === A. Milestones achieved === || '''Milestone''' || '''Status''' || '''Begin Date''' || '''End Date''' || '''Notes''' || || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April 2012 || June 15, 2012 || First rack is Rob's InstaGENI rack || || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || Complete || June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || Complete || July 1, 2012 || Aug 22, 2012 || Did not use UEN aggregate switch - Used only ProtoGENI direct connection into the GENI backbone. Could not interrupt the experiments for the data plane cutover || || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) || || 9/23/2012 || Sept 30, 2012 || || || Make Switch resources available to NSF experimenters || || Sept 23, 2012 || Sept 23, 2012 || || === B. Deliverables made === * GEC 12: attended by Steve Corbato and Joe Breen with poster * GEC 13: attended by Steve Corbato and Joe Breen * GEC 14: attended by Steve Corbato and Joe Breen * FOAM and Flowvisor installation complete == II. Description of work performed during last quarter == A. Activities and findings B. Project participants C. Publications (individual and organizational) D. Outreach activities E. Collaborations F. Other Contributions