Changes between Initial Version and Version 2 of Ticket #32
- Timestamp:
- 02/17/09 14:20:59 (15 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
Ticket #32
-
Property
Status
changed from
new
toassigned
- Property Owner changed from somebody to Vic Thomas
-
Property
Status
changed from
-
Ticket #32 – Description
initial v2 1 1 PI indicated that he might need to adjust delivery date for this milestone because he started the project at less than full staffing (on risk funding). Vic Thomas has requested updated date from Paul Barford. 2 3 - Emailed Barford on 15 Jan 2009 asking about milestone delivery. He responded they'd be completed "next week". 4 - Emailed Barford on 30 jan 2009 asking about milestone delivery. He responded they'd be completed "next week". Set milestone due date to 30 Jan based on comment by Barford that delivery dates may be delayed given they got under contract on Oct. 27 and not Oct. 1. 5 - Emailed Barford on 17 Feb 2009 asking about milestone delivery.