Opened 15 years ago
Closed 15 years ago
#158 closed (fixed)
Set installation dates for first 3 nodes.
Reported by: | hdempsey@bbn.com | Owned by: | hdempsey@bbn.com |
---|---|---|---|
Priority: | major | Milestone: | SPP: Deploy three SPP nodes - |
Component: | SPP | Version: | SPIRAL1 |
Keywords: | Cc: | Jon Turner, ricci@cs.utah.edu | |
Dependencies: |
Description
SPP and ProtoGENI nodes will be installed at 3 I2 PoPs. SPPs were ready to ship on 7/7. I2 installation dates are tied to ProtoGENI node installation dates in the deployment plan. See ticket #157 for ProtoGENI status.
Note: See
TracTickets for help on using
tickets.
SPP node for first node shipped. First node is Washington D.C., but was originally expected to be Kansas. SPP equipment for remaining nodes is ready to ship, but is being held at WUSTL in order to make/test any changes that GMOC might request after staging the first node for wht D.C. installation. No issues with shipping remaining SPP equipment to Bloomington by 8/15.