Custom Query (1408 matches)

Filters
Β 
Or
Β 
Β Β 
Β 
Columns

Show under each result:


Results (101 - 200 of 1408)

Ticket Summary Owner Priority Milestone Component Version
#70 Upgrade lab software to become a GENI prototype system griff@netlab.uky.edu major INSTOOLS: S1.a Upgrade UKY Emulab INSTOOLS SPIRAL1
#71 Produce first implementation of UKY Aggregate Manager griff@netlab.uky.edu major INSTOOLS: S1.b Develop Reference implementation of Aggregate Manager (AM v1.0) INSTOOLS SPIRAL1
#72 Extend DRAGON/GRMS as an aggregate manager to include optical and edge compute resources Peter O'Neil major MAX: Extend DRAGON/GRMS MAX SPIRAL1
#73 Purchase virtualization servers and complete end-to-end VLAN connections with backbone Peter O'Neil major MAX: Purchase virtualization servers and connections MAX SPIRAL1
#74 Extend ProtoGENI clearinghouse to support topology creation feamster@cc.gatech.edu major BGPMux: Define RSpec - BGPMUX SPIRAL1
#75 Implement component manager that supports the ProtoGENI API feamster@cc.gatech.edu major BGPMux: Integrate with ProtoGENI - BGPMUX SPIRAL1
#76 Change in milestone date. somebody major GushProto: GEC Demo - GPO SPIRAL1
#77 Track veritical integration for Ciena switch James Sterbenz, jpgs@ittc.ku.edu major GpENI: Delivery of component manager ICD for Ciena Core Director switch GPENI SPIRAL1
#78 Temporary tunnels in use for CMU lab hdempsey@bbn.com major CMU Lab: Get CMU ProtoGENI node on I2 VLAN GPO SPIRAL1
#79 Post updated draft of Measurement Document pb@cs.wisc.edu major MeasurementSys: S1.b Measurement system design specification - MeasurementSys SPIRAL1
#80 Propose date for 2nd draft of measurement system design document pb@cs.wisc.edu major MeasurementSys: S1.b Measurement system design specification - MeasurementSys SPIRAL1
#81 Update CMU Milestone #1 hdempsey@bbn.com major CMU Lab: desired node config & boot mgmt functionality GPO SPIRAL1
#82 Update CMU Milestone #1 hdempsey@bbn.com major CMU Lab: IP-in-IP encap from CMU-Control to Homenet nodes GPO SPIRAL1
#83 Status of ticket hdempsey@bbn.com major CMU Lab: Tunneling packets from Utah to CMU GPO SPIRAL1
#84 Duplicate task? hdempsey@bbn.com major CMU Lab: IP-in-IP encap from CMU-Control to Homenet nodes GPO SPIRAL1
#85 modify milestone to add an extra protoGENI node to I2 in Spiral 1 somebody major ProtoGENI: Integrate, install 3 nodes in I2 - GPO SPIRAL1
#86 Status update for task 6: Emulator user interface integration pgunn@cs.cmu.edu major CMU Lab: Emulator user interface integration CMULAB SPIRAL1
#87 milestone 1a completion hmussman@bbn.com major ORBIT: 1a Extend OMF to support multiple heterogeneous testbeds ORBIT SPIRAL1
#88 milesrone 1b completion hmussman@bbn.com major ORBIT: 1b Extend OMF interfaces and software to support mobile testbeds ORBIT SPIRAL1
#89 milestone 1e completion hmussman@bbn.com major ORBIT: 1e Establish OMF operating environment, verify, and demo ORBIT SPIRAL1
#90 milestone 1c completion gruteser@winlab.rutgers.edu major ORBIT: 1c provide reference implementations of extended OMF software to WiMAX project ORBIT SPIRAL1
#91 milestone 1d completion Ivan Seskar major ORBIT: 1d Provide VLAN connections to the GENI backbone ORBIT SPIRAL1
#92 milestone 1f completion gruteser@winlab.rutgers.edu major ORBIT: 1f Support experimentation by other GENI users ORBIT SPIRAL1
#93 milestone 1b completion hmussman@bbn.com major WiMAX: 1b Validate open API capabilities of the WiMAX base station WIMAX SPIRAL1
#94 milestone 1c completion hmussman@bbn.com major WiMAX: 1c Import a GENI-compliant control framework from the ORBIT project WIMAX SPIRAL1
#95 milestone 1e completion Ivan Seskar major WiMAX: 1e Demo basic functionality of base station WIMAX SPIRAL1
#96 milestone 1a completion hmussman@bbn.com major ORCABEN: 1a Extend ORCA as a GENI control framework ORCABEN SPIRAL1
#97 milestone 1b completion hmussman@bbn.com major ORCABEN: 1b Make an early reference implementation of ORCA available ORCABEN SPIRAL1
#98 milestone 1c completion Ilia Baldine major ORCABEN SPIRAL1
#99 milestone 1d completion Ilia Baldine major ORCABEN SPIRAL1
#100 milestone 1e completion Ilia Baldine major ORCABEN SPIRAL1
#101 milestone 1f completion Ilia Baldine major ORCABEN: 1f All ORCA assigned prototypes integrated into ORCA clearinghouse ORCABEN SPIRAL1
#102 milestone 1c completion blynn@cs.umass.edu major DOME: 1c Implement, integrate and document virtualized access to the WiFi radio DOME SPIRAL1
#103 milestone 1d completion blynn@cs.umass.edu major DOME: 1d Import and setup a GENI-compliant control framework based on ORCA DOME SPIRAL1
#104 milestone 1d completion hmussman@bbn.com major VISE SPIRAL1
#105 milestone 1e completion David Irwin major ViSE: S1.e Contingent upon availability of reference implementation of Shirako/ORCA at 6 months, import and then integrate VISE SPIRAL1
#106 milestone 1f completion David Irwin major ViSE: S1.f Complete Xen sensor virtualization VISE SPIRAL1
#107 Hold discussions with GMOC on security for initial data sharing Stephen.Schwab@cobham.com major SECARCH: S1.b Security Contributions to GMOC documents GPO SPIRAL1
#108 Provide information on prototype clearinghouse and where/how it will operate. jtw@ISI.EDU major TIED SPIRAL1
#109 Identify GENI TIED release v 0.1 jtw@ISI.EDU major TIED: S1.c Release v 0.1 of component manager and clearinghouse. TIED SPIRAL1
#110 Explain how GENI users can access DETER via TIED jtw@ISI.EDU major TIED: S1.e Provide user access to DETER via TIED. TIED SPIRAL1
#111 Publish version of Common Operational Dataset that incorporates feedback from control framework projects somebody major GMOC:Define Common Operational Dataset GMOC SPIRAL1
#112 Feedback from ProtoGENI on Common Operational Dataset somebody major GMOC:Define Common Operational Dataset GMOC SPIRAL1
#113 Define specialized operational dataset jph@grnoc.iu.edu major GMOC: S1.b.b Define Specialized Operational Dataset GMOC SPIRAL1
#114 Define GMOC native data format and make availble to other GENI projects for comment jph@grnoc.iu.edu major GMOC: S1.a.c Define GMOC Native Operational Data Format GMOC SPIRAL1
#115 Develop alternate spiral-1 outreach milestone Aaron Falk major BGPMux: Virtual Network with BGPMux How-To -- GPO SPIRAL1
#116 milestone 1a completion anish@cse.ohio-state.edu major KANSEI SPIRAL1
#117 milestone 1b completion anish@cse.ohio-state.edu major KANSEI: 1b Establish Kansei testbed clearinghouse KANSEI SPIRAL1
#118 milestone 1c1 completion anish@cse.ohio-state.edu major KANSEI SPIRAL1
#119 milestone 1c2 completion hmussman@bbn.com major KANSEI SPIRAL1
#120 milestone 1d1 completion anish@cse.ohio-state.edu major KANSEI SPIRAL1
#121 milestone 1d2 completion anish@cse.ohio-state.edu major KANSEI SPIRAL1
#122 Plan for GEC5 demonstrations hdempsey@bbn.com major GPO SPIRAL1
#124 ProtoGENI control plane integration status pgunn@cs.cmu.edu major CMU Lab: integrate with ProtoGENI control plane GPO SPIRAL1
#125 Dataplane tunnelling 4a somebody major CMU Lab: integration of node-CMU and CMU-Utah tunnels GPO SPIRAL1
#126 Dataplane tunnelling 4b somebody major CMU Lab: integration of node-CMU and CMU-Utah tunnels GPO SPIRAL1
#127 Dataplane tunnelling 4c pgunn@cs.cmu.edu major CMU Lab: integration of node-CMU and CMU-Utah tunnels GPO SPIRAL1
#128 Ticket for Miletone: student testbed use prs@cs.cmu.edu major CMU Lab: student testbed use GPO SPIRAL1
#130 Requirements for GMOC demo at GEC5 cviecco@grnoc.iu.edu major GMOC: S1.b Demonstrate initial GMOC Framework Implementation at a GEC GMOC SPIRAL1
#131 PlanetLab/Geniwrapper Demo hdempsey@geni.net major PLANETLAB SPIRAL1
#132 MANFRED/MAX GEC5 demo Christopher Small major MAX: Make a working prototype MAX SPIRAL1
#133 GEC 5 Demo requirements for Million Node GENI project hdempsey@bbn.com major MILNGENI SPIRAL1
#134 Requirement for KanseiGenie demo at GEC 5 hdempsey@bbn.com major KANSEI SPIRAL1
#135 Demonstration of the proposed GENI Federated Clearinghouse by CNRI hdempsey@geni.net major DigitalObjectRegistry: Adapt digital object architecture to meet clearinghouse registry needs. DIGOBREG SPIRAL1
#136 GEC5 DOME Demo Description and Needs hdempsey@bbn.com major DOME SPIRAL1
#137 ViSE GEC5 Demonstration hdempsey@geni.net major VISE SPIRAL1
#138 Gush demo hdempsey@geni.net major GUSH SPIRAL1
#139 UMLPEN GEC5 Demo Requirements hdempsey@geni.net major UMLPEN SPIRAL1
#140 Demo resources request for GEC5 hdempsey@geni.net major TIED SPIRAL1
#141 Document how OpenFlow Hypervisor meets version 0 Component Manager requirements for GENI seethara@stanford.edu ΒΆ major ENTGENI: Version 0 Aggregate Component Manager GPO SPIRAL1
#142 Document draft protocol between EntGENI FlowVisor and PlanetLab clearinghouse appenz@cs.stanford.edu major ENTGENI: Draft API/protocol between ENTGENI AM and Clearinghouse GPO SPIRAL1
#143 Provide description of Enterprise GENI network at Stanford appenz@cs.stanford.edu major ENTGENI: S1.a Deploy Phase 0 Enterprise GENI network at Stanford GPO SPIRAL1
#144 Document state of integration for inteface between ENTGENI AM and PlanetLab clearinghouse appenz@cs.stanford.edu major ENTGENI: S1.b Start integrating interfaces from ENTGENI AM to Clearinghouse GPO SPIRAL1
#145 milestone 1e completion hmussman@bbn.com major DOME: 1e Implement, integrate and document a first release (v1.0) of the software GPO SPIRAL1
#146 GEC5 Demo for GIMS hdempsey@bbn.com major MeasurementSys SPIRAL1
#147 milestone 1g completion David Irwin major ViSE: S1.g Contingent upon available budget, provide a VLAN connection from your testbed to the Internet2 VISE SPIRAL1
#148 milestone 1h completion David Irwin major ViSE: S1.h Virtualization of actuators; single guest VM; demo VISE SPIRAL1
#149 milestone 1i completion David Irwin major ViSE: S1.i Testbed available for public use within our cluster VISE SPIRAL1
#150 1g milestone completion hmussman@bbn.com major DOME: 1g provide a VLAN connection from your testbed's server to the Internet2 backbone network DOME SPIRAL1
#151 1outreach activities blynn@cs.umass.edu major DOME: 1g provide a VLAN connection from your testbed's server to the Internet2 backbone network DOME SPIRAL1
#152 1outreach activites David Irwin major VISE SPIRAL1
#153 Explain what GENI content will be incuded in the teacher education program and when. jtw@isi.edu major TIED: S1.f Participate in NSF TRUST Science and Technology Center's teacher education program. TIED SPIRAL1
#154 ORBIT GEC5 demonstration hdempsey@bbn.com major ORBIT SPIRAL1
#155 DTUNNELS GEC5 demo feamster@cc.gatech.edu major BGPMUX SPIRAL1
#156 Raven GEC5 demo requirements hdempsey@bbn.com major RAVEN SPIRAL1
#157 schedule node installations chsmall@grnoc.iu.edu major ProtoGENI: Integrate, install 3 nodes in I2 - PROTOGENI SPIRAL1
#158 Set installation dates for first 3 nodes. hdempsey@bbn.com major SPP: Deploy three SPP nodes - SPP SPIRAL1
#159 Document outreach activities Yan_Luo@uml.edu major UMLPEN: GENI Outreach UMLPEN SPIRAL1
#160 ORCA-BEN Demo at GDC5 hdempsey@geni.net major ORCABEN SPIRAL1
#161 modify milestone to add an extra protoGENI node to I2 in Spiral 1 somebody major SPP: Deploy three SPP nodes - SPP SPIRAL1
#162 First SPP node shipped chsmall@grnoc.iu.edu major SPP: Deploy three SPP nodes - SPP SPIRAL1
#163 1out ORBIT outreach for year 1 hmussman@bbn.com major ORBIT: 1f Support experimentation by other GENI users GPO SPIRAL1
#164 Get feedback on specialized operational dataset definitions cviecco@grnoc.iu.edu major GMOC: S1.a.a Complete initial GMOC Operational Dataset Translater Implementation GMOC SPIRAL1
#165 Get feedback on GMOC internal data format from GENI projects jtw@isi.edu major GMOC: S1.b.b Complete initial GMOC Data Exchanger Implementation GMOC SPIRAL1
#166 Discuss security architecture for GMOC data sharing with SPARTA. somebody major GMOC: S1.a.d Integrate Security services in GMOC framework GPO SPIRAL1
#167 Document what security services will be included in GMOC Spiral 1 data sharing design and prototype. jph@grnoc.iu.edu major GMOC: S1.a.d Integrate Security services in GMOC framework GMOC SPIRAL1
#168 GEC5 GpENI demo resource request hdempsey@bbn.com major GPENI SPIRAL1
#169 Work in progress for this report Stephen.Schwab@cobham.com major SECARCH: S1.c Revised Security Design Report SECARCH SPIRAL1
#170 Presented Opt-In requrements at GEC4 Opt-in Working Group meeting. somebody major REGOPT: S1.a Produce opt-in requirements document GPO SPIRAL1
#172 milestone 1d completion Ivan Seskar major WiMAX: 1d First release v1.0 of GENI base station node software WIMAX SPIRAL1
Note: See TracQuery for help on using queries.