#31 fixed Possible change to milestone date Vic Thomas Vic Thomas
Description

PI indicated that he might need to adjust delivery date for this milestone because he started the project at less than full staffing (on risk funding). Vic Thomas has requested updated date from Paul Barford.

See Ticket #32.

#32 fixed Possible change to milestone date. Vic Thomas Vic Thomas
Description

PI indicated that he might need to adjust delivery date for this milestone because he started the project at less than full staffing (on risk funding). Vic Thomas has requested updated date from Paul Barford.

  • Emailed Barford on 15 Jan 2009 asking about milestone delivery. He responded they'd be completed "next week".
  • Emailed Barford on 30 jan 2009 asking about milestone delivery. He responded they'd be completed "next week". Set milestone due date to 30 Jan based on comment by Barford that delivery dates may be delayed given they got under contract on Oct. 27 and not Oct. 1.
  • Emailed Barford on 17 Feb 2009 asking about milestone delivery.
#33 fixed Waiting for release ricci@flux.utah.edu Aaron Falk
Description

Initial implementation is complete. Necessary tasks include finishing documentation and verifying the right license is in the right places.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19