Custom Query (1408 matches)

Filters
 
Or
 
  
 
Columns

Show under each result:


Results (43 - 45 of 1408)

Ticket Resolution Summary Owner Reporter
#9 fixed Milestone date change. Vic Thomas Vic Thomas
Description

Change milestone date from 11/14/2008 to 12/17/2008. Delay will allow code to take advantage of PlanetLab GENI wrapper.

#10 fixed Develop and document an approach to integration with one or more control frameworks. Vic Thomas hdempsey@bbn.com
Description

Work with U. Washington on developing an approach to integrating with one or more control frameworks.

Had telecon with 2/6/09. The project will most likely integrate w/ ProtoGENI. Discussions with ProtoGENI during GEC. Plan for proof-of-concept demo at July GEC. Details of this telecon emailed to gpo-tech on 2/9/09.

#11 fixed Adjust due date for design specification if necessary. Vic Thomas hdempsey@bbn.com
Description

PI indicated that he might need to adjust delivery date for this milestone because he started the project at less than full staffing (on risk funding). Vic Thomas has requested updated date from Paul Barford.