Changes between Version 16 and Version 17 of WiMAXInteg/CampusInstallation


Ignore:
Timestamp:
11/30/09 14:11:18 (14 years ago)
Author:
hmussman@bbn.com
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • WiMAXInteg/CampusInstallation

    v16 v17  
    55
    66
    7 === 7.1  License ===
     7=== 7.1  Obtain FCC License ===
    88
    99Each campus must apply to the FCC and obtain a license (experimental authorization) to operate the WiMAX equipment at their location.
     
    3232Here is a sample license, the [attachment:Winlab-WiMax-License.pdf WINLAB Rutgers WiMAX license] received from the FCC.
    3333
     34=== 7.2  Identify Outdoor Site on Campus ===
    3435
    35 === 7.2  Antenna ===
     36
     37=== 7.3  Identify Indoor Equipment Room on Campus ===
     38
     39
     40=== 7.4  Install Wiring Between Outdoor Site and Indoor Equipment Room ===
     41
     42
     43=== 7.5  Install Pole at Outdoor Site and Ground ===
     44
     45
     46=== 7.6  Install Antenna at Outdoor Site ===
    3647
    3748[[Image(Antenna.jpg, height=160px, align=right)]]
     
    4253The installation should be performed by qualified PE to ensure proper grounding and should follow [attachment:ANTENNA.pdf NEC's mounting instructions].
    4354
    44 === 7.3  Base Station Outdoor and Indoor Units ===
     55
     56=== 7.7  Install Base Station Outdoor Unit ===
    4557
    4658The Outdoor Unit (ODU) is mounted outdoors, near the antenna.  It connects to the antenna with a coaxial cable, and connects to the Indoor Unit (IDU) with two fibers.  In addition, it requires a -48 power feed and a protection ground.
     59
     60The installation should be performed by qualified PE to ensure proper grounding and should follow [attachment:BS_INSTALLATION.pdf NEC's installation instructions]
     61
     62=== 7.8 Complete Wiring of Base Station Outdoor Unit ===
     63
     64=== 7.9  Install Indoor Equipment Racks and Ground ===
     65
     66=== 7.10 Install 120VAC and -48VDC Power Feeds and/or Supplies ===
     67 
     68=== 7.11 Install Base Station Indoor Unit ===
    4769
    4870The Indoor Unit (IDU) is mounted indoors, typically in an equipment room.  It connects to the ODU with two fibers, and to the Linux servers usxing an ethernet cable.  In addition, it requires a -48 power feed and a protection ground.
     
    5173The installation should be performed by qualified PE to ensure proper grounding and should follow [attachment:BS_INSTALLATION.pdf NEC's installation instructions]
    5274
    53 === 7.4  Linux Server(s) and Software ===
     75=== 7.12  Complete Wiring of Base Station Indoor Unit ===
     76
     77=== 7.13  Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units ===
     78
     79 
     80
     81=== 7.14  Install Linux Server(s) and Software ===
    5482
    5583
    56 === 7.5  Backbone Network Connectivity ===
     84=== 7.15  Connect Backbone Network ===
    5785
    5886
    59 === 7.6 Reference Client Platform ===
     87=== 7.16  Provide Reference Client Platform ===
    6088
    6189
    62 === 7.7 Inital Check-Out ===
     90=== 7.17 Inital Check-Out of Campus WiMAX Testbed ===