Project Number
1751
Project Title
Campus deployment of an open GENI WiMAX 802.16e Testbed in Polytechnic Institute of NYU
a.k.a WIMXNYUPT
Technical Contacts
PI: Thanasis Korakis korakis@poly.edu
Participating Organizations
Polytechnic University of NYU, Brooklyn, NY
Related Projects
Open GENI WiMAX Base Station Kit for Campus Deployments
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This project builds an open/programmable WiMax testbed on the campus of Polytechnic University of NYU. It utilizes the "Open GENI WiMax Base Station Kit for Campus Deployments" provided by an associated project (Rutgers and NEC). It provides for the installation, maintenance and integration of the WiMax base station kit with existing experimentation facilities at the university.
Current Capabilities
Milestones
Spiral 4
- MilestoneDate(WIMXNYUPT: S4.a Demonstration at GEC12 and Experimenter Outreach)?
- MilestoneDate(WIMXNYUPT: S4.b Documentation and Code Release)?
- MilestoneDate(WIMXNYUPT: S4.c Demonstration at GEC13 and Experimenter Outreach)?
- MilestoneDate(WIMXNYUPT: S4.d Documentation and Code Release)?
- MilestoneDate(WIMXNYUPT: S4.e Demonstration at GEC14 and Experimenter Outreach)?
- MilestoneDate(WIMXNYUPT: S4.f Final report and code release)?
Campus Installation Checklist
Polytechnic University of NYU
Contact(s):
PI: Thanasis Korakis korakis@poly.edu
Step | Description | Planned | Started | Completed | Comment |
1 | Identify Outdoor Site on Campus | - | Started | Completed | Roof of the ECE building |
2 | Obtain FCC License | - | Started | Completed | |
3 | Identify Indoor Equipment Room on Campus | - | Started | Completed | Networking room of the Library in the ECE building |
4 | Install Wiring at Outdoor Site and to Indoor Equipment Room | - | Started | Completed | |
5 | Install Pole at Outdoor Site and Ground | - | Started | Completed | |
6 | Install Antenna at Outdoor Site | - | Started | Completed | |
7 | Install Base Station Outdoor Unit | - | Started | Completed | |
8 | Complete Wiring at Outdoor Site and to Indoor Equipment Room | - | Started | Completed | |
9 | Install Indoor Equipment Racks and Ground | - | Started | Completed | |
10 | Install 120VAC and -48VDC Power Feeds and/or Supplies | - | Started | Completed | |
11 | Install Base Station Indoor Unit | - | Started | Completed | |
12 | Complete Wiring of Base Station Indoor Unit | - | Started | Completed | |
13 | Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units | - | Started | Completed | |
14 | Install Ethernet (VLAN) Switch, or Identify Existing Capacity | - | Started | Completed | |
15 | Install Linux Server(s) and Software | - | Started | Completed | |
16 | Connect Backbone Network | - | Started | Completed | |
17 | Provide Reference Client Platform | - | Started | Completed | |
18 | Initial Check-Out of Campus WiMAX Testbed | - | Started | Completed |
Status Reports and Demos
Quarterly Status Reports:
- March 2012 quarterly status report
Other Reports and Demos:
- Status Update at GEC13 WiMAX Planning Meeting (March 2012)
- Demo/Poster at GEC13 Demo Session (March 2012)
- Throughput Experiment Using BitTorrent Presentation at GEC12 WiMAX Planning Meeting (November 2011)
- Poster at GEC12 Demo Session (November 2011)
- Status Update at GEC11 WiMAX Planning Meeting (July 2011)
- Spiral 2 Review
- ParkNet demo at GEC9 (video)
Project Technical Documents
Software Releases
Connectivity
Attachments (1)
- GENI_WiMAX_Poly_review_Sept_2010.pdf (449.5 KB) - added by 14 years ago.
Download all attachments as: .zip