Version 23 (modified by 12 years ago) (diff) | ,
---|
ExoGENI Acceptance Test Status
This page captures test status as the ExoGENI Acceptance Test Plan is executed.
The following matrix captures the state for each of the tests cases. For overall project details see the ExoGENI Project page.
Test | State | Date Completed | Tickets |
EG-ADM-1 | In progress | ||
EG-ADM-2 | |||
EG-MON-1 | |||
EG-MON-2 | |||
EG-MON-3 | |||
EG-EXP-1 | |||
EG-EXP-2 | |||
EG-EXP-3 | |||
EG-EXP-4 | |||
EG-EXP-5 | |||
EG-EXP-6 | |||
EG-ADM-3 | |||
EG-ADM-4 | |||
EG-ADM-5 | |||
EG-ADM-6 | |||
EG-ADM-7 | |||
EG-MON-4 | |||
EG-MON-5 |
State Legend Description Color(green,Pass)? Test completed and met all criteria Color( #98FB98, #100000 , Pass)? Test completed and met most criteria. Exceptions documented Color( #E0EEEE, #100000 , Complete)? Test completed with workaround for ticketed issue(s) Color(#CAE1FF,Workaround)? Test in progress with workaround for ticketed issue(s). Color(#63B8FF,In Progress)? Currently under test. Color(red,Fail)? Test completed and failed to meet criteria. Color(orange,Blocked)? Blocked by ticketed issue(s).