Changes between Version 13 and Version 14 of GEMINIv1.1IntegrationTasks


Ignore:
Timestamp:
10/11/12 17:13:38 (11 years ago)
Author:
Jeanne Ohren
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • GEMINIv1.1IntegrationTasks

    v13 v14  
    2121|| 6 || Run Acceptance tests on all supported configurations || Jeanne || 10/22 || [[Color(#B0E0E6, In Progress)]] || ||
    2222|| 7 || Compose tutorial wiki || Jeremy and Ahmed || 10/12 || [[Color(#B0E0E6, In Progress)]] || 1st draft by 10/12, iterate the week before GEC ||
    23 || 8 || Define topology, produce initial rspec || Jim and Charles || 10/10 || [[Color(green,Complete)]] || ||
     23|| 8 || Define topology, produce initial rspec || Jim and Charles || 10/10 || [[Color(green,Complete)]] || [attachment:four_node_rspec.xml] ||
    2424|| 9 || Set up and verify half of slices for tutorial || Ezra || 10/12 || Not started || ||
    2525|| 10 || Set up rest of slices for tutorial || Ezra || 10/15 || Not started || ||