wiki:2012-09_UEN_GENI_Status_Report

Version 6 (modified by joe.breen@utah.edu, 12 years ago) (diff)

--

Project 1861 Univ of Utah/UEN GENI Regional Project Status Report

Period: Through 9/30/2012

  1. Major accomplishments ¶
  1. Milestones achieved
Milestone Status Begin Date End Date Notes
Acquire and test HP aggregate switch for ProtoGENI and first GENI rack Complete April 2012 June 15, 2012 First rack is Rob's InstaGENI rack
Deploy aggregate switch and bring new connections to Univ of Utah and UEN Complete June 15, 2012 July 6, 2012 Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure
Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) Complete July 8, 2012
Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) Aug 30, 2012
Make Switch resources available to NSF experimenters Sept 30, 2012
  1. Deliverables made
    • GEC 12: attended by Steve Corbato and Joe Breen with poster
    • GEC 13: attended by Steve Corbato and Joe Breen
    • GEC 14: attended by Steve Corbato and Joe Breen
    • FOAM and Flowvisor installation complete
  1. Description of work performed during last quarter
  2. Activities and findings
  3. Project participants
  4. Publications (individual and organizational)
  5. Outreach activities
  6. Collaborations
  7. Other Contributions