Description

ProtoGENI will install and support an additional ProtoGENI node in I2 before October 2009, bringing the total to 3. Also modify ship date to be 7/15 instead of 7/1. Final installation date will depend on scheduling with I2, but ProtoGENI nodes should be ready to pack for I2 by 7/15, so that will be the due date for this milestone. Will update date again when I2 confirms an installation date.

Contract-visible milestone change approved by Henry Yeh on April 14, 2009.

Change History (1)

comment:1 Changed 15 years ago by hdempsey@bbn.com

Resolution: fixed