Ticket #85 (closed task: fixed)

Opened 1 year ago

Last modified 1 year ago

modify milestone to add an extra protoGENI node to I2 in Spiral 1

Reported by: hdempsey@bbn.com Assigned to: somebody
Priority: major Milestone: ProtoGENI: Integrate, install 3 nodes in I2 -
Component: GPO Version: SPIRAL1
Keywords: Cc: ricci@cs.utah.edu, falk@bbn.com
Dependencies:

Description

ProtoGENI will install and support an additional ProtoGENI node in I2 before October 2009, bringing the total to 3. Also modify ship date to be 7/15 instead of 7/1. Final installation date will depend on scheduling with I2, but ProtoGENI nodes should be ready to pack for I2 by 7/15, so that will be the due date for this milestone. Will update date again when I2 confirms an installation date.

Contract-visible milestone change approved by Henry Yeh on April 14, 2009.

Change History

04/23/09 14:19:47 changed by hdempsey@bbn.com

  • status changed from new to closed.
  • resolution set to fixed.