SALT install

Reported by: Josh Karlin Owned by: Josh Karlin
Priority: major Milestone: ProtoGENI: Integrate, install 3 nodes in I2 -
Component: PROTOGENI Version: SPIRAL1
Keywords: Cc:
Dependencies:

Description

The SALT installation began today (9/2/09) and is expected to finish by Friday the 4th. John Graham at IU GlobalNOC will configure the I2 wave to directly connect the WASH and SALT sites, with testing available by early next week.

The SALT IP address assignments and wiring diagrams are available in ticket #173

Change History (2)

comment:1 Changed 15 years ago by Josh Karlin

Node is installed and so far everything appears to be up. Also, WASH was pingable from SALT over the GENI wave.

comment:2 Changed 15 years ago by ricci@cs.utah.edu

Resolution: fixed
Status: newclosed

This install was completed on September 4th.